In December, China added 9.6GW grid-connected photovoltaic projects

According to incomplete statistics, as of December 28, 2022, the “nominal” scale of new grid-connected domestic ground power stations exceeds 9.6GW. However, many projects are partially connected to the grid, but not fully connected to the grid. Due to statistical reasons, there may be certain errors.

The previous article introduced the details of 5GW grid-connected projects, and this article introduces the details of 4.6GW new grid-connected photovoltaic projects in December. If you want to know about the previous 5GW projects, please refer to the previous article “New 5GW Photovoltaic Projects Connected to the Grid in December”

1. National Energy Group: 276MW

On the afternoon of December 9th, the 220 kV transmission project of the 90MW photovoltaic project in Zhongbu Town and Mingkou Town, Leping City, undertaken by Hebei Engineering Company, was successfully transmitted at one time, marking the completion of the main work of the project. The 90WM photovoltaic project of Zhongbu Town and Mingkou Town, Leping City of Guoneng is located in Leping City, Jingdezhen City, Jiangxi Province. The machinery company undertakes the 220 kV transmission project of the project. The line starts from Guoneng Leping Zhongbu Photovoltaic Power Station and ends at 220kV Hejia Substation. The total length of the line path is 25.73km, of which the overhead line is 25.58km, and the cable line is 0.15km long. The main projects are 220 kV transmission line project and opposite side interval reconstruction project. The project started construction on August 2, 2022, and successfully delivered electricity on December 9, 2022, which took 4 months.

On December 12, the first batch of power units of the Huayan Phase I 100MW photovoltaic project of the “Hanchuan City New Energy Million-kilowatt Base” of China Energy Group Hubei Company was successfully connected to the grid. It is reported that the project is located in Huayan Farm, Hanchuan City, Hubei Province. It consists of contiguous fish farms, covers a total area of about 2,470 mu, has a planned installed capacity of 100 megawatts, and operates with a fixed photovoltaic array.

On December 26, one of the major projects in 2022 in Guoluo Prefecture, Qinghai Province, the Guoluo “Photovoltaic, Animal Husbandry and Storage” photovoltaic power station, was fully connected to the grid for power generation. It is reported that the project was undertaken by the Fourth Bureau of Hydropower. The project is located in Maqin County, Guoluo Prefecture, Qinghai Province, about 30 kilometers away from Maqin County, at an altitude of about 4,000 meters, with a total of 86 megawatts.

2. Huadian Luodian Nawei 100MW Agricultural Photovoltaic Power Station

On December 9, Luodian Nawei 100MW Agricultural Photovoltaic Power Plant was successfully connected to the grid for the first time. It is reported that the project is located in Dalang Village, Luozhen Town, Luodian County, Guizhou Province. The total installed photovoltaic capacity is 100MW (nameplate power is 141.2964MWp), and there are 2 plots in total. 1# plot covers an area of 220.16 mu and is arranged in 32 square array, 22,960 pieces of components to be installed; the 2# plot covers an area of 2,132.2 mu, with 29 square arrays, and 238,840 pieces of components to be installed;

3. Jingneng Group: 150MW

At about 15:00 on December 10, the 448th inverter of Jingneng International Damaoqi Aodu 100MW photovoltaic power generation project was officially connected to the grid, successfully realizing full-capacity grid-connected power generation. It is reported that this project is one of the key projects of Damao Banner. As the first centralized photovoltaic grid-connected project in the autonomous region in the “14th Five-Year Plan” and the first grid-connected power generation project in the autonomous region’s guaranteed new energy indicators in 2021, Baotou City The first centralized new energy project for grid-connected power generation in 2022, the project officially started construction on July 12, 2022, and successfully realized the first unit of 23.7MW grid-connected power generation on October 10.

At 3:20 p.m. on December 24, the 50MW fourth-phase expansion project of Qingshuihe Kangshengzhuang Photovoltaic Power Generation Project of United New Energy in Hohhot, Inner Mongolia, undertaken by Shandong Electric Power Construction No. The project construction task was successfully completed and the production and operation stage was formally entered.

Jingneng Qingshuihe Photovoltaic Project is located in Qingshuihe County, Hohhot City, Inner Mongolia. A 7.5MW/15MWh energy storage system will be built for a 50MW photovoltaic project. It will be connected to the 110kV step-up station of the preliminary project in the form of expansion, and will be sent out by the built-up step-up station. .

4. Photovoltaic power generation project in Dongle North Beach, Shandan County, Tianju, Gansu

On December 10, the Dongle Beitan Photovoltaic Power Generation Project in Shandan County was successfully connected to the grid for power generation. The project is located in Shandan County, Zhangye City, Gansu Province. A 110kV step-up station will be built as a supporting facility. The photovoltaic area is composed of 16 photovoltaic power generation units (including 15 4.133MWp power generation units and 1 2.925MWp power generation unit). The cable collector line is connected to the 35kV side of the newly built 110kV step-up station.

5. CGNPC Ali 100MW Photovoltaic Project

At 18:05 on December 12, the Tibet Ali 100MW photovoltaic project was fully put into operation. At present, the Tibet Autonomous Region is in a critical period of energy green and low-carbon transformation and development. This project meets the core needs of the Tibet Autonomous Region government, and is also a positive response to the new energy requirements of China General Nuclear Power Group to “be bigger, stronger and better”, and implement CGN’s new energy “dream pursuit” It is of great significance to carry out the specific measures of the meeting spirit of the 14th Five-Year Development Symposium on Voyage and Sprint, and at the same time enhance the power supply guarantee capacity of the Ali area, improve the energy structure of the Ali area, promote the economic transformation and development of the Ali area, and promote the construction of a clean, low-carbon, safe and efficient energy system. .

6. Datang Group: more than 370 MW

On December 14, the Datang Daye Jinshandian 85 MW integrated power generation project of agriculture, light and storage, undertaken by Jiangxi Hydropower, was successfully connected to the grid for power generation. After the completion of the project, it will play an important role in promoting the transformation of the local economic structure and improving the power structure. Make positive contributions to the local energy conservation and emission reduction, environmental protection to achieve the goal of “carbon peak, carbon neutrality” and the construction of ecological civilization, with high social and environmental benefits. The project is located in Jinshandian Town, Daye City, Hubei Province, with a construction scale of 85 MW.

On December 18, the 100-megawatt photovoltaic power generation project (Phase I) in Tiandong, Guangxi was successfully connected to the grid for power generation, laying a solid foundation for the next step of full-capacity grid-connected power generation. Guangxi Tiandong Photovoltaic Power Generation Project is located in Xinjian Village and Lixin Village, Tiandong County, Baise City, Guangxi Zhuang Autonomous Region, with a total investment of about 420 million yuan and an area of 1,450 mu. Adopt 185,472 540W single crystal double glass modules, set up 23 photovoltaic power generation units, 368 sets of 196kW string inverters, 23 sets of 3150kV box type transformers, the installed capacity of DC side is 100.15MW, and the installed capacity of AC side is 72.13MW watt. The total length of the 35 kV collector line is 22.16 kilometers, and then through the 110 kV step-up station, it is connected to “Dongping Station” by an overhead line.

On December 23, when the winter solstice came, Datang Huaibei Wugou Photovoltaic Power Generation Project ushered in a major milestone node, and it was successfully connected to the grid for the first time.

Datang Huaibei Wugou Photovoltaic Power Generation Project is located in Suixi County, Anhui Province. The planned module capacity of the photovoltaic area is 85MW, and 205,920 photovoltaic modules are actually installed. Matching sent out to build a 110kV step-up station.

On December 27, Datang’s 100 MW fishery-solar-solar-storage integrated power generation project in Xiongkou Management District, Qianjiang City, Hubei, undertaken by Jiangxi Hydropower, was successfully connected to the grid and put into operation. Qianjiang Xiongkou Fishery Photovoltaic Storage Integrated Power Generation Project is a key new energy project in Hubei Province, and it is also another important milestone for Jiangxi Hydropower to actively promote the development of the photovoltaic industry and help achieve the “double carbon target”.

On December 27, Datang Yangcheng Dongye Baisang 100MW photovoltaic EPC project realized grid-connected power generation, adding new impetus to the low-carbon and green development of the local economy. The Dongye and Baisang projects are located in Dongye Town and Baisang Town, Yangcheng County, Shanxi Province, with an average elevation of about 680 meters and a total area of about 2,800 mu. The project adopts block-based power generation and centralized grid connection, and a supporting 110 kV step-up station will be built. After the project is fully put into operation, the annual average power generation is 163.7 million kilowatt-hours, and the annual average equivalent utilization hours are 1319 hours. It can save about 49,138.06 tons of standard coal, reduce carbon dioxide emissions by about 135,937.87 tons, reduce sulfur dioxide emissions by about 32.33 tons, and reduce nitrogen oxide emissions. About 30.71 tons.

At 14:08 on December 27, good news came from Huashanling, Lianyuan City, Hunan Province. The Lianyuan Project of Datang Huayin Loudi Ecological Governance Photovoltaic Power Generation Base was officially connected to the grid for power generation after intensive and orderly grid-connected operations, marking the The three sub-projects of Tanghuayin Loudi Ecological Governance Photovoltaic Power Generation Base Project have all been connected to the grid for power generation.

7. 290MW Rural Revitalization Distributed Photovoltaic Power Station Project in Youjiang District, Baise City, Guangxi

At 17:18 on December 14, the 290MW rural revitalization distributed photovoltaic power station project in Youjiang District, Baise City, Guangxi, invested and developed by Power Construction New Energy Group, successfully realized grid-connected power generation. So far, the installed capacity of Power Construction New Energy Group has reached 9 million kilowatts!

8. Huayang New Energy: 120 MW Photovoltaic Composite Power Generation Project in Zhongdong, Huazhou, Guangdong

At 19:38 on December 14, the step-up station of Guangdong Huazhou Zhongdong 120 MW Photovoltaic Composite Power Generation Project contracted by Energy China Southwest Research Institute was successfully connected to the grid. It is reported that the project is located in Zhongdong Town and Hejiang Town, Huazhou City, with a construction capacity of 120 MW. The project flexibly adopts the grid-connected method, and the grid-connected power generation is 8 months ahead of schedule. The construction of the project is of great significance to actively explore the organic combination of new energy projects and rural revitalization.

9. Guangxi Rongan Yuchai New Energy Co., Ltd. Tantou Township 100MW Photovoltaic Project

On December 16, Guangxi Rong’an Yuchai New Energy Co., Ltd.’s Tantou Township photovoltaic project was successfully connected to the grid. It is the first project in Guangxi that has been approved for photovoltaic construction indicators in the same batch to achieve grid-connected power generation. As a major project in the autonomous region, Liuzhou Rongan Tantou Township Photovoltaic Power Generation Project is also the only approved centralized power generation project in Liuzhou City in 2022. The area is about 2000 mu.

10. CNNC: 350MW

At 21:43 on December 17, 2022, the 170MW animal husbandry-solar complementary photovoltaic power generation project in Weizhou Town of China Nuclear Power Co., Ltd. was successfully connected to the grid. This project is the first batch of full-capacity grid-connected projects in Ningxia Hui Autonomous Region’s 2022 annual guarantee indicators, and it is also the first animal husbandry and photovoltaic complementary project invested and constructed by CNNC Huineng in Ningxia.

On December 20, the Fuchuan Shijia 80MW Agricultural Photovoltaic Project of CNNC Huineng Guangxi Company was successfully connected to the grid for power generation. Fuchuan Shijia Photovoltaic Project is located in Shijia Township, Fuchuan County, Hezhou City, Guangxi Zhuang Autonomous Region. It is the seventh project of CNNC Huineng Guangxi Company in Fuchuan County after Changchun, Changguang, Chaodong, Shijia, Xinzao Wind Farm and Longwan Photovoltaic Power Station. . The successful grid-connected power generation of the project marks that CNNC Huineng Guangxi’s installed capacity of new energy in Fuchuan County has reached 373,500 kilowatts, accounting for 56% of the total installed capacity of new energy in Fuchuan County.

On December 26, 2022, CNNC Huineng’s 100MW agriculture-solar hybrid power generation project in Yanggan Town, Suixi County, Zhanjiang was successfully connected to the grid! The project is developed and constructed by CNNC Huineng Shanxi Company. It is located in Yanggan Town, Suixi County, Zhanjiang City, Guangdong Province, covering a total area of about 1,400 mu. The installed capacity of the project is 100MWp, and the installed capacity of the AC side is 100MW. It adopts block-based power generation and centralized grid connection scheme. The total power generation during the 25-year operation period is about 312 million kWh, which is equivalent to burning 1.1 million tons of standard coal and reducing carbon dioxide emissions by 2.86 million tons .

11. Simao Dadi 100MW Photovoltaic Power Generation Project in Southern Province

On December 20, the first batch of phalanxes of the Simao Dadi Photovoltaic Power Generation Project in Yunnan Province, undertaken by the First Bureau of Hydropower, successfully realized grid-connected power generation. Simao Photovoltaic Power Generation Project has an installed capacity of 128.7 MW and a rated capacity of 100 MW. The project site is equipped with 31 photovoltaic sub-arrays. sub-square. The project boosts the voltage to 35 kV locally through 31 box-type transformers, and connects it to the No. 1 plot with 5 circuits of 35 kV converging lines. The boost station is equipped with a 100MVA main transformer.

12. Jinzhou Electric Power: Guizhou Jinpu Huiyilong New District Agricultural Photovoltaic Power Station Project

On December 23, the agricultural photovoltaic power station in Guizhou Jinpuhui Yilong New District, which was constructed by China Hydropower Fourth Bureau, was connected to the grid at full capacity for power generation. The project is located in Qianxiang Township, Anlong County, Qianxinan Prefecture, Guizhou Province, with a planned total installed capacity of 50 MW. The project adopts the “agricultural and photovoltaic complementary” mode of photovoltaic power station construction, organically combines photovoltaics with agriculture and high efficiency, improves land utilization, and forms a new model of industrial coordinated green development of “agricultural and photovoltaic integration”.

13. China Resources Power: 25MW

At 14:18 on December 23, the 25MW tea-solar complementary photovoltaic power generation project in Eryuan Town, Wencheng County, Zhejiang Company of China Resources Power was successfully connected to the grid for power generation, marking another major milestone node of the project and laying the foundation for the full-capacity grid connection of subsequent projects. solid foundation. China Resources Power Wencheng Tea Photovoltaic Complementary Photovoltaic Power Generation Project is located in Banshan Village, Eryuan Town, Wencheng County, Wenzhou City, Zhejiang Province. It uses Xiaolongyi Forest Land to build a tea photovoltaic complementary photovoltaic power station, covering an area of 375 mu, with a construction capacity of 25MWp.

14. State Power Investment Corporation: 502MW

On December 23, two projects of the Yellow River Company received good news of grid connection one after another: at 9:19, the #20 sub-array in Zone I of the second phase of the National Photovoltaic and Energy Storage Demonstration Experiment Platform (Daqing Base) was successfully connected to the grid; 18:06 The first batch of 500,000-kilowatt photovoltaic projects in Gonghe County, Hainan base, were successfully connected to the grid for power generation, and the operation indicators of all system equipment were normal.

The first batch of 500,000-kilowatt projects of the 1,000,000-kilowatt photovoltaic project in Gonghe County, Hainan Base: The project is located in the desertified grassland area about 43 kilometers south of Gonghe County. A total of 326,000 single-crystal double-sided double-glass modules with specifications of 545W, 570W, and 595W were installed in the 35kV collection station.

The second phase project of the National Photovoltaic and Energy Storage Demonstration Experimental Platform (Daqing Base): The installed capacity of the #20 sub-array in this grid-connected area is 2.0358 MW, and the N-IBC double glass + 166mm + half-chip + 120 The latest battery components, mainly carry out the full-cycle demonstration and experiment of the latest battery component technology route in the industry, which is of great significance to accelerate the promotion and application of new technologies and new products, promote technological innovation, and drive the development of the entire industry chain.

15. Huaneng Group: 320MW

On December 25, Huaneng Guangzhou Huadu Chini Fishing Solar Complementary Project

The first batch of phalanxes were successfully connected to the grid

Issued the first “green electricity”

It marks Huaneng’s development in the Guangdong-Hong Kong-Macao Greater Bay Area

A breakthrough has been made in the construction of the first photovoltaic base

It is reported that the project covers an area of 6,000 mu, with a planned installed capacity of 320,000 kilowatts and an average annual on-grid electricity of 320 million kwh, which can save 110,000 tons of standard coal and reduce carbon dioxide emissions by 280,000 tons. ” mode to achieve win-win results in environmental benefits, social benefits and economic benefits.

16. Gulang County, Gansu: 750MW

At 18:11 pm on December 25, the equipment in the 330 kV collection booster station in Huanghuatan, Gulang County was officially launched, marking the launch of the 330 kV collection station for the first batch of new energy projects in the county’s “14th Five-Year Plan” In operation, the first batch of national large-scale base projects, the 300,000-kilowatt photovoltaic sand control project of Elion Group, the 300,000-kilowatt Jiayu Group, and the 150,000-kilowatt Xinhua Hydropower 2 provincial “14th Five-Year Plan” first batch of new energy competition index projects Realize grid-connected power generation and become the first grid-connected photovoltaic power station in the city’s “14th Five-Year Plan” new energy project.

17. Guangdong Energy Friendly May Day Farm Photovoltaic Composite Project

December 26 at 14:33

Photovoltaic Composite Project of Guangdong Energy Friendly May Day Farm

Successfully connected to the grid for power generation

  1. Power China:

Public farm photovoltaic power generation project in Xinping County, Yunnan Province

On December 26, the first batch of public farming photovoltaic power generation projects in Xinping County, Yunnan Province, which was contracted by the Kunming Institute for EPC engineering, was connected to the grid for power generation. energy project. The power station is located in Dingju Village, Yangwu Town, Xinping Yi and Dai Autonomous County, Yuxi City, Yunnan Province. The total installed capacity of the DC side of the whole plant is 53MWp.

19. Investment in Tibet: Yilian Photovoltaic 100MW Photovoltaic Project in Yongren County, Chuxiong Prefecture

On December 26, 2022, the Yilian Photovoltaic 100 MW construction general contracting project undertaken by Shanghai Electric Power Construction Co., Ltd. in Yongren County, Chuxiong Prefecture, Yunnan Province was successfully connected to the grid. The project is located in Lianchi Township, Yongren County, Chuxiong Prefecture, Yunnan Province, including two areas in the south (Maichong) and north (Ban Sanjie). The site is divided into 14 plots, with an installed capacity of 103.3 MW on the AC side and an installed capacity on the DC side. About 131.19 MW; use monocrystalline silicon double-sided double-glass solar cell modules of more than 500 watts, and set up a total of 32 photovoltaic power generation units with different installed capacities, all of which adopt fixed operation mode, with 3~4 circuits of 35 kV collector lines Access to a new 220 kV (or 500 kV) booster station.

20. Start investment in Tibet: Jitang 20MW animal husbandry and photovoltaic complementary (with energy storage) composite guaranteed supply photovoltaic power generation project in Chaya County, Qamdo, Tibet

On December 27, the 20-megawatt grazing-solar complementary (with energy storage) composite photovoltaic power generation project with guaranteed power supply in Jitang, Chaya County, Qamdo, Tibet, undertaken by China Hydropower Fourth Bureau, was connected to the grid for power generation.

21. 20 MW Photovoltaic Project in Liangzhou District, Wuwei, Gansu

On December 26, the 20 MW photovoltaic project in Liangzhou District, Wuwei, Gansu Province, undertaken by China Hydropower Bureau 4, was fully connected to the grid for power generation.

The project is located in Qinglin Township, Fengle Town, Northwest Liangzhou District, Wuwei City, Gansu Province, adjacent to Yongchang County in the north. The landform of the site area is a Gobi desert with flat terrain. The designed installed capacity is 20 MW, consisting of six 3.3 MW photovoltaic power generation units Composition, equipped with 4 MW/8 MWh energy storage device. The project plans to install 36,972 double-sided double-glass solar cell modules, all of which use monocrystalline silicon solar cells.

22. 125.3MW parity photovoltaic project in Jingke Nahe City

On December 28, the 125.3MW parity photovoltaic project in Jinkona River City was connected to the grid for power generation.